Appendix 1: Programme Update

 

Bin infrastructure and litter reduction

 

Project objectives

Reducing litter and improving the cleanliness of the city

Overall RAG status (including explanation)

Previous report

This report

Amber

Red

Project start date

June 2021

Project end date

June 2026

 

Reporting period

October 2023 to February 2024

Key planned activities

Hold Spring Clean Up

Update website pages to provide information on how to organise a community clean-up, providing resources and information on health and safety and public liability insurance

(RAG status is Red as the resource allocated to this project has been reallocated to Digital Cityclean. When resources are available, delivery will recommence)

 

Key achievements since the last update

Completed Bin Amnesty Trial

Updated website to include an option for residents to include return unused bins and boxes

Held City Centre Big Clean event in November 2023

Started planning for the Spring Clean Up

Held workshops to review bin expenditure, creating an action plan

Completed roll out of anti-litter and anti-fly tip signs

Started audit of on-street litter bins

Key dependencies

Fleet Strategy

Carbon Neutral Fund

Key risks and issues

Limited resources to carry out projects

Competing priorities

Budget restrictions

 

 

 

Customer experience

 

Project objectives

Improving the customer experience and providing a consistent service to everyone who contacts Cityclean

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

April 2019

Project end date

Ongoing

 

Reporting period

October 2023 to February 2024

Key planned activities

Deliver further training to Environmental Service Advisors on Contact Management to respond to councillor enquiries

Review Waste Assessment Process

Continue to develop Standard Operating Procedures to improve the customer experience and provide a consistent service

 

Key achievements since the last update

Cityclean responded to 95.6% of Stage 1 Complaints within 10 days (City Environment overall 93.4%)

From June to November 2023, City Environment received 198 complaints, which is 72 fewer than the same period last year; of these, Cityclean received 175 complaints, which is 60 fewer than the same period last year

Environmental Service Advisors received training on Contact Management to respond to councillor enquiries

Continued to respond to emails within 24 to 48 hours on average (working days)

Scheduled regular meetings with Street Cleansing operations to improve Contact Management response times

Key dependencies

Digital Cityclean

Graffiti reduction

Waste minimisation

Management Framework

Key risks and issues

Loss of support for project

Industrial action

 

 

 

Digital Cityclean

 

Project objectives

Modernising the service and supporting the wider programme of change through technology

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2020

Project end date

February 2025

 

Reporting period

October 2023 to February 2024

Key planned activities

Continue to implement the Trade Waste module

Plan for next phase of the Programme

 

Key achievements since the last update

Continued to implement the Trade Waste module, including populating system with full Trade Waste datasets – rounds, events, attributes, and accounts

Installed nine mounting kits in collection vehicles

Reviewed programme resources and completed service redesign

Key dependencies

Customer experience

Management Framework

Key risks and issues

Project Team capacity

IT&D resources and capacity

Implementation timescales

Existing poor data

Withdrawal of support from workforce or trade unions

 

 

 

Environmental enforcement

 

Project objectives

Addressing anti-social and illegal behaviour to improve the environment and minimise waste clean-up and disposal costs

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

September 2019

Project end date

Ongoing

Reporting period

October 2023 to February 2024

Key planned activities

Continue to deliver the Environmental Enforcement Framework

Continue to provide further advice and guidance

Key achievements since the last update

Completed public consultation on phase 2 of managing commercial bins on the highway

Reported the outcomes of the consultation to Committee who agreed to extend the T-Zone area

Continued to meet with local businesses on individual and group basis to offer further advice and guidance

Continued to reduce the number of commercial bins on the highway across the T-Zone area

Increased Fixed Penalty Notice amounts for some offences in line with changes in legislation, following Committee approval

Introduced an offence of engine idling

Completed six-night shifts, issuing over 80 Fixed Penalty Notices

See also Flyering and Graffiti reduction updates

Key dependencies

Customer experience

Flyering

Graffiti reduction

Key risks and issues

Perception of service and its objectives

 

 

 

Fleet Strategy

 

Project objectives

Delivering of a 10-year strategy and green procurement plan, providing cost and savings projections. The strategy includes the migration to new technology as it develops, such as hydrogen fuel cells, to reduce maintenance and carbon emissions

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

March 2022

Project end date

March 2030

Reporting period

October 2023 to February 2024

Key planned activities

Receive three more electric communal waste vehicles

Start requirements for food waste collection vehicles

Continue work on Accident Reduction Policy

Continue to work with other service on the procurement of new electric vehicles

Key achievements since the last update

72 electric vehicles in operation across the council

Four electric refuse collection trucks working daily

Received delivery of first electric communal waste vehicle

Received delivery of top-loader for the collection of glass

Received second electric van in City Parks to transport ride-on mowers

Continued to deliver Certificate of Professional Competence (CPC) training

Started work on Accident Reduction Policy

Key dependencies

Customer experience

Digital Cityclean

Food waste

Health & Safety

Hollingdean Depot

Operator’s Licence

Procurement review

Key risks and issues

Resources – both time and finance

Power infrastructure implemented and available

Competing priorities e.g. service delivery and modernisation and improvement work

Brexit – vehicles purchased from Europe

Delays with contracts

 

 

 

Flyering

 

Project objectives

Improving the flyering service by reviewing the flyering framework and extending the current flyering zones

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

March 2022

Project end date

March 2024

Reporting period

October 2023 to February 2024

Key planned activities

Implement online payments

Review and update terms and conditions

Key achievements since the last update

Received approval from Committee to extend the flyering licence area

Implemented the extension of the flyering licence area

Reviewed and updated webpage

Key dependencies

Environmental Enforcement

Key risks and issues

Decrease in flyering licences

Resources - staff, and possibly budget

 

 

 

Food waste

 

Project objectives

Complete cost analysis of a citywide food waste collection service

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2021

Project end date

March 2024

 

Reporting period

October 2023 to February 2024

Key planned activities

Await further announcements from government on resource/revenue and ongoing funding

Continue to meet other local authorities to understand good practice, risks and issues

Finalise projected yields to inform the number of vehicles required

Finalise estimated cost

Prepare to move project to phase two, developing implementation plans

 

Key achievements since the last update

Met with other local authorities to understand how food waste has been introduced

Reviewed food waste collection study completed by Eunomia in 2021

Completed analysis on expected food waste yields  

Completed DEFRA request to enable payment of capital funding allocated

Met with finance colleagues to determine staffing costs

Contacted suppliers to determine capital costs based on market price

Key dependencies

Digital Cityclean

Fleet strategy

Customer experience

Procurement review

Key risks and issues

Capital funding gap

Resources, revenue and ongoing funding

Data availability

 

 

 

Graffiti reduction

 

Project objectives

Delivering the aims of Graffiti Reduction Strategy, reducing the amount of graffiti vandalism around Brighton & Hove

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

November 2018

Project end date

December 2023

 

Reporting period

October 2023 to February 2024

Key planned activities

Continue to review consultation feedback and prepare new draft Strategy and action plan

Take draft Strategy and action plan to committee for approval

Commission mural for York Hill

 

Key achievements since the last update

Received approval to commence public consultation on reviewing and updating the Graffiti Tagging Reduction Strategy

Held public consultation on the council’s consultation portal from 21 November 2023 to 9 January 2024

Held Reimagine Brighton & Hove event as part of the consultation activities on 21 November

Reviewed consultation feedback

Continued community engagement activities, meeting with various LATs and Resident Associations to discuss partnership work

Continued working with Sussex Police and ongoing Joint Action Group

Engaged with the Immediate Justice Programme, led by Sussex Police; a prolific tagger completed nine hours of Immediate Justice to remove graffiti in hotspot area

Continued enforcement action and investigation of prolific taggers

Installed CCTV camera at Queens Park for reduction and prevention of graffiti

Increased graffiti patrols at The Level

Continued work with Statutory Undertakers for graffiti removal

Key dependencies

Customer experience

Environmental enforcement

Digital Cityclean

Key risks and issues

Commercial property owners and Statutory Undertakers do not comply with Community Protection Warnings

Challenges to identify and catch taggers

Murals getting tagged and limited resource for ongoing maintenance

 

 

 

Health & Safety

 

Project objectives

Improving health & safety compliance and performance across City Environmental Management

Overall RAG status (including explanation)

Previous report

This report

Amber

Green

Project start date

January 2021

Project end date

Ongoing

 

Reporting period

October 2023 to February 2024

Key planned activities

Use information from City Parks H&S review to formulate a plan of action to reduce health & safety risks going forward

Work with new Training & Engagement Officer to increase staff training, including completing the City Parks training matrix

Introduce maintenance regime for City Parks work equipment to help manage Hand Arm Vibration risk

Update noise action plans

Undertake City Parks Stage 2 Fire Risk Assessments

Deliver mop-up session for ‘back of vehicle’ refresher training for outstanding Collections operational staff

Undertake further priority audits on a risk basis

 

Key achievements since the last update

Started a full review of City Parks H&S management using the Corporate Risk Profile template

Procured new battery powered equipment such as grass trimmers for City Parks in keeping with the council’s commitment to using greener technology; this also results in lower Hand Arm Vibration and noise levels

Started a review of Cityclean and City Parks Risk Assessments

Delivered ‘back of vehicle’ refresher training to the majority of Collections operational staff

Started delivery of programme of testing Hand Arm Vibration levels for City Parks machinery

Key dependencies

Fleet Strategy

Hollingdean Depot

Management Framework

Operator’s Licence

Key risks and issues

Constantly emerging new priorities and risks e.g. incident investigation, union raised issues

Ongoing need for modernisation of the service including health and safety performance management, with suitable and sufficient risk assessments backed up by a working, evidencable training matrix

Health & Safety Executive interventions and recommendations

Resources to deliver priorities

 

 

 

Hollingdean Depot

 

Project objectives

Improving safety and security at Hollingdean Depot and ensuring the infrastructure is fit for purpose

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

November 2019

Project end date

ongoing

 

Reporting period

October 2023 to February 2024

Key planned activities

Assess current concrete base at the location of the old offices to determine suitability for future plans

Redevelop wash bay

Refurbish depot heating and hot water system

 

Key achievements since the last update

Demolished old offices

Started planning for the redevelopment of the wash bay

Key dependencies

Health & Safety

Operator’s Licence

Key risks and issues

Staff working in portacabins which are coming to end of life and do not provide sufficient space

Resources – both time and finance

 

 

 

Management Framework

 

Project objectives

Improving management processes at Cityclean to ensure BHCC policies and processes are followed

Overall RAG status (including explanation)

Previous report

This report

Amber

Green

Project start date

July 2022

Project end date

Ongoing

 

Reporting period

October 2023 to February 2024

Key planned activities

Continued to manage the outcome of the Independent Inquiry

Complete the formal consultation with Trade Unions and staff regarding start and finish at the Depot, issue outcome document and implement agreed changes

Continue to performance management of crews

Continue to carefully manage collection of missed work

Complete remaining Annual Performance Review for frontline operational staff

Complete the formal consultation on moving Communal Recycling to a 4-on-4-off-rota to improve reliability of collections, issue outcome document and implement agreed changes

Deliver mop-up session for ‘back of vehicle’ refresher training for outstanding Collections operational staff

Commence procurement for traffic management to enable twice yearly A27 litter pick

Review learning offer for frontline operational staff

 

 

Key achievements since the last update

Continued to manage the outcome of the Independent Inquiry including: the development of a culture change programme and actioning individual disciplinary cases

Received approval of action plan to deliver Independent Inquiry recommendations from Strategy, Finance & City Regeneration Committee

Started formal consultation with Trade Unions and staff regarding start and finish at the Depot

Continued to performance manage crews

Continued to carefully manage collection of missed work by meeting with crews and instructing them to collect their own missed work when there is capacity within their working week to do so

New Training & Engagement Officer started

Started Annual Performance Reviews for all frontline operational staff; in Collections, all Driver Supervisors have been completed and now focusing on Operatives; in Street Cleansing, the majority are complete

Started formal consultation on moving communal recycling collections to a 4-on-4-off-rota to improve reliability of collections

Delivered ‘back of vehicle’ refresher training to the majority of Collections operational staff

Reviewed collection frequency of seafront bins

Reviewed delivery model for public toilets

Reviewed approach to weed management

Started seasonal recruitment; open day held for people to drop-in and get support to complete an application form

Key dependencies

Political support

Customer Experience

Hollingdean Depot

Operator’s Licence

Key risks and issues

Unofficial and industrial action

Withdrawal of support from workforce or trade unions

HSE (Health & Safety Executive) interventions and recommendations

 

 

 

Operator’s Licence

 

Project objectives

Maintaining the current standing of the BHCC Operator’s Licence

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

September 2019

Project end date

Ongoing

 

Reporting period

October 2023 to February 2024

Key planned activities

Continue to comply with Operator’s Licence

Continue work on Accident Reduction Policy

Key achievements since the last update

Maintained good standing with Traffic Commissioner

Continued to comply with the Operator’s Licence with a score of 98.3 out of 100

Continued to deliver Certificate of Professional Competence (CPC) training

Started work on Accident Reduction Policy

Key dependencies

Fleet Strategy

Health & Safety

Hollingdean Depot

Management Framework

Key risks and issues

Withdrawal of support from workforce or trade unions

HSE (Health & Safety Executive) interventions and recommendations

 

 

 

Procurement Review

 

Project objectives

Improving the procurement and contract management in Cityclean to deliver value for money and comply with council policies and procedures

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2022

Project end date

Ongoing

 

Reporting period

October 2023 to February 2024

Key planned activities

Issue tender documents for textile recycling contract (subject to Committee approval)

Complete procurement of weed management contract and enter contract management arrangements

Enter contract management arrangements for the Allotment Service software

Support procurement food waste containers

Review options for PPE contract as it approaches its expiry date

Support Fleet with future compliant procurement of spare vehicle parts and maintenance

Further refine and deliver programme of compliance across service

Continue maintaining contract register for Cityclean and report on upcoming actions required

Continue contract management of PPE contract, external recycling providers and toilet consumables suppliers, including the expansion of WEEE and carton containers

 

Key achievements since the last update

Maintained regular contract management of key external suppliers, including clinical waste, carton recycling, textile recycling, PPE and uniform supply, public toilet consumables (ongoing regular contract meetings)

Supported delivery of new fuel contract for depot

Advised on procurement of new WEEE and carton containers

Started tender process for weed management contract

Reviewed textile contract

Maintained Cityclean contract register (ongoing)

Supported Fleet with procurement projects (ongoing)

Identified further areas of non-compliance in City Environment (ongoing)

Key dependencies

Fleet Strategy

Food waste

Recycling points

Key risks and issues

Competing and varying priorities

 

 

 

Public toilets

 

Project objectives

Identifying opportunities and delivering actions to sustain public toilet provision

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

January 2022

Project end date

June 2025

Reporting period

October 2023 to February 2024

Key planned activities

Start delivery of Phase 2 of the Refurbishment Programme

Complete installation of Changing Places Toilets at Preston Park and St Ann’s Well Gardens

Implement ‘single shift’ delivery model

Continue to manage resources dynamically to provide as much provision as possible

Continue options appraisal work

 

Key achievements since the last update

Finalised sites for Phase 2 of the Refurbishment Programme

Received approval to create new public toilets at The MacLaren Pavilion at The Level, which will form part of Phase 2

Published tender documents for Phase 2 of the Refurbishment Programme

Finalised revised sites for Changing Places locations

Published tender documents for new Changing Places Toilets

Opened Changing Places Toilet at The One Garden at Stanmer Park in partnership with Plumpton College

Agreed arrangements for reopening the Royal Pavilion Garden Toilets

Designed the ‘single shift’ delivery model to deliver savings, whilst keeping all existing sites open

Started staff consultation on ‘single shift’ delivery model

Key dependencies

Customer Experience

Key risks and issues

Staffing levels

Resources – both finance and time

Unbudgeted costs (such as utilities & unexpected maintenance costs) putting public toilets budget at risk of overspend

Supply chain issues

Cost of refurbishment exceeds agreed budget due to cost inflation

Closure of sites for refurbishment may lead to complaints

Refurbishment contractor unable to maintain/recruit sufficient staffing levels

Contractor not delivering on the agreed specification and/or timescales

Unforeseen work issues may exceed agreed budget

 

 

 

Recycling points

 

Project objectives

Reviewing and improving recycling point locations

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

June 2022

Project end date

December 2024

 

Reporting period

October 2023 to February 2024

Key planned activities

 

Produce effective signage for new WEEE bins; to include messaging on batteries and vapes (which CANNOT be placed in these bins)

Rollout the additional carton and WEEE recycling bins

Publish new user-friendly map of all recycling points

Develop next steps for phase 2 of improving Recycling Points, to include: review of site signage, review of dry mixed and glass recycling capacities within areas of kerbside collections, monitoring of 21 WEEE bins, and continuing to apply consistency in dry mixed and glass recycling bin lid colours and signage

 

Key achievements since the last update

Received Committee approval to expand carton recycling to a further 47 locations across the city (a new total of 68 locations)

Received Committee approval to introduce a new WEEE recycling service to 21 locations, one for each ward of the city

Started preparation for rollout of these services, including procurement of bins and lids, preparing signage and liaising with contractors

Reduced the number of complaints about overflowing carton bins following introduction of more bins at hotspots in July 2023

Key dependencies

Procurement review

Food waste

Bin infrastructure

Waste minimisation

Key risks and issues

Simpler recycling

Budget restrictions

Bin vandalism and waste theft (WEEE)

Increased fly-tipping

Graffiti tagging

 

 

 

 

 

 

Waste minimisation

 

Project objectives

Reducing contamination and increase recycling rates in the city

Overall RAG status (including explanation)

Previous report

This report

N/A

Amber

Project start date

September 2023

Project end date

Ongoing

 

Reporting period

October 2023 to February 2024

Key planned activities

Finalise and agree Communications Campaign plan with stakeholders

Develop resources toolkit for use in engagement activities across all forms of media and to support face to face work with harder to reach communities

Continue to develop contamination communication trial pilot for the kerbside with input from stakeholders within the service

Complete website review of content and format for A-Z

Continue to research and develop Private Sector / HMO / Student communications

Key achievements since the last update

Completed research on best practice and successful contamination reduction campaigns from other authorities and waste partnerships informed by WRAP research and behaviour change / decision science

Reviewed website content, including A-Z content and format

Redesigned Recycling flyer for insertion with Council tax bill with emphasis on addressing contamination and QR code link to ‘What you can and can’t recycle in Brighton and Hove’ page (renamed ‘Thank you for recycling!’ page)

Developed ideas for how to better engage residents with what contamination is and how to prevent it as part of a rolling communications campaign plan

Started developing a kerbside collection pilot for contamination communication strategy based on areas with high contamination rates

Started research into Private Sector / HMO / Student communications, with a focus on engagement actions to reach transient renters

Developed plans for truck signage

Started building relationships with internal and external stakeholders

(See also content in main report)

Key dependencies

Bin infrastructure and litter reduction

Customer experience

Recycling points

Key risks and issues

Budget restrictions

Crew training and engagement

Resources – both time and finance

Web Design Team schedule

 

 

 

 

 

 

Weed management

 

Project objectives

Implementing a new approach to weed management

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

January 2024

Project end date

March 2025

 

Reporting period

October 2023 to February 2024

Key planned activities

Continue procurement process

Appoint contractor to treat weeds across the city using a controlled-droplet application

Manage contractors in line with the contract

 

Key achievements since the last update

Delivered 2023 Weeding Plan, using the traffic light system and completed a review of 2023 Weeding Plan

Presented report to CESS Committee in January 2024 on options for managing weeds in 2024; Committee agree a new approach to weed management

Prepared a specification for the procurement of a controlled-droplet application to manage and remove weeds from across the city in 2024

Key dependencies

Customer experience

Key risks and issues

Costs

Availability of contractor willing / able to take on contract

Timing and weather for completing the treatment